Skip to main content

§ 1225

Graves Farms, In re

Ruling
Confirmation denied as plan failed to meet the best interests test and secured claims treatmentwas insufficient. (Bankr. D. Kan.)
Issue(s)
Confirmation of Plan; Conditions.

ABI Membership is required to access the full summary of Graves Farms, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Commercial opinion summary, case decided on March 28, 2019 , LexisNexis #0519-095

Akers, In re

Ruling
Debtor's fourth amended plan could not be confirmed where plan was not feasible and wasfraught with unreasonable delay and mismanagement by debtor that was prejudicial to hiscreditors. (Bankr. W.D. Va.)
Issue(s)
Confirmation of Plan; Conditions; Debtor's Ability to Comply With Plan.

ABI Membership is required to access the full summary of Akers, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on January 03, 2019 , LexisNexis #0219-066

Morris, In re

Ruling
Confirmation of chapter 12 plan denied where debtor has history of being unable to make timely payments and the amounts provided to the court did not show that debtor has reasonable chance of successfully carrying out his duties and obligations under the plan. (Bankr. N.D. Miss.)
Issue(s)
Confirmation of Plan; Conditions; Debtor's Ability to Comply With Plan.

ABI Membership is required to access the full summary of Morris, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on September 14, 2018 , LexisNexis #1018-111

Blake, In re

Ruling
Court denied confirmation of debtors’ amended plan as it failed to pay a secured creditor the value of its claim as of the effective date of the plan. (Bankr. S.D. Ill.)
Issue(s)
Confirmation of Plan; Conditions; Allowed Secured Claimholders.

ABI Membership is required to access the full summary of Blake, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on March 06, 2018 , LexisNexis #0418-052

Johnson, In re

Ruling
Confirmation of debtor's plan was denied because it is not feasible and it proposes aninadequate interest rate on secured creditor's claims. (Bankr. W.D. Wis.)
Issue(s)
Confirmation of Plan.

ABI Membership is required to access the full summary of Johnson, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on January 12, 2018 , LexisNexis #0218-088

Mortellite, In re

Ruling
Court denied confirmation of the debtors' amended plan where it undervalued a farm whenevidence showed that the farm was worth more than the amount of the bank's secured claim.(Bankr. D.N.J.)
Issue(s)
Confirmation of Plan.

ABI Membership is required to access the full summary of Mortellite, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on January 11, 2018 , LexisNexis #0218-087

Furman, In re

Ruling
Confirmation denied as plan was not feasible because debtor could not fund secured creditor's payment without nephew's help. (Bankr. D. Kan.)
Issue(s)
Confirmation of Plan; Conditions; Debtor's Ability to Comply With Plan.

ABI Membership is required to access the full summary of Furman, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on December 15, 2017 , LexisNexis #0218-055

Penick, In re

Ruling
Confirmation of debtors' plan was denied as debtors' failed to carry their burden to prove thefeasibility of their plan. (Bankr. E.D. Ky.)
Issue(s)
Confirmation of Plan; Conditions; Debtor's Ability to Comply With Plan.

ABI Membership is required to access the full summary of Penick, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on August 28, 2017 , LexisNexis #1017-026

In re Elkhorn Crossing, LLC

Ruling
Confirmation of chapter 12 plan denied. (Bankr. D. Neb.)
Issue(s)
Confirmation of Plan.

ABI Membership is required to access the full summary of In re Elkhorn Crossing, LLC Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Commercial opinion summary, case decided on November 21, 2016 , LexisNexis #1216-081

In re Meinders

Ruling
Confirmation of chapter 12 plan denied due to lack of feasibility.
Issue(s)
Should chapter 12 debtor's plan be confirmed over bank's objection on feasibility grounds?

ABI Membership is required to access the full summary of In re Meinders Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on April 18, 2016 , LexisNexis #0516-061