Skip to main content

§ 1129(a)(6)

Ultra Petro. Corp., In re--FERC v. Ultra Res., Inc.

Ruling
Bankruptcy court was not required to obtain Federal Energy Regulatory Commission approvalprior to confirming plan that called for rejection of natural gas pipeline contract. (5th Cir.)
Issue(s)
Confirmation of Plan; Requirements; Regulatory Commission Approval of Rate

ABI Membership is required to access the full summary of Ultra Petro. Corp., In re--FERC v. Ultra Res., Inc. Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

:
Judge or Jurisdiction information not available
Commercial opinion summary, case decided on March 14, 2022 , LexisNexis #0522-021

Beyha, In re

Ruling
The 180-day deadline for seeking revocation of an order of confirmation applied even if fraudwas discovered after the expiration of the deadline. (Bankr. E.D. Pa.)
Issue(s)
Confirmation of Plan; Requirements; Regulatory Commission Approval of Rate

ABI Membership is required to access the full summary of Beyha, In re Please sign in if you are already an ABI member, or otherwise you may Become an ABI Member

Consumer opinion summary, case decided on March 10, 2022 , LexisNexis #0522-022